Monday, 20 August 2012
Aims and objectives of maintenance:
The purpose of maintenance is to maintain the steam turbine in order to achieve as high a plant availability as possible at the minimum cost. Maintenance of steam turbines used in power station may be classified broadly in three categories:
- Rectification of defects: The defects may or may not be urgent. If immediate repairs are needed, these may be carried out on running limits or the units should be shut down. If the repairs are not urgent, it may be carried out in planned program of future work.
- Planned preventive maintenance on running units: A system of routine maintenance is adopted to prevent the defects and breakdowns. The planning of such system needs careful consideration in order to arrive at the optimum level of maintenance. The actual work content of each maintenance routine can only be determined after experience with the plant over a period of time. After carrying out the preventive maintenance, it is recorded on a record card with full particulars or the items attended.
- Planned preventive maintenance on shut down units: In order to minimize the maintenance cost of shut down units, it is necessary to plan the work to be done carefully in advance so that the duration of the plant shut down is reduced to a minimum. This planning process should start some weeks or months before the shutdown is due to take place.
Steam turbine overhaul:
Following is the sequence of events of a typical turbine overhaul:
- Remove pipe works mounted on turbine and all top half cylinders and covers.
- Remove coupling bolts and bearings covers leaving thrust bearing assembled.
- Measure all relevant blade and gland clearances on the horizontal joints with fillers or tapered gauges.
- Remove the thrust bearings and then the turbine rotors to have a detailed examination of fixed and moving blades and diaphragms gland segments, casings, bearings, bolts,etc. concerning any type irregularities and damages.
- Re-form all gland and baffle segment knife-edge and restore all radial clearances. Examine the bedding of all bearings to journals and measure oil clearances. Check the adhesion of wright metal of journal bearings.
- After cleaning the blade deposits by water washing, chemical washing or blasting process, refit the rotors and measure clearances on the bottom points of glands and blades with lead or plastic strip. Measure similar clearances on the horizontal joint and compare for eccentricity of the shaft in the casing.
- After cleaning the bearings, check the wear down of bearings with the help of appropriate bridge gauge and filler gauges and compare the figures with those taken on the irection of previous overhaul
- Check the alignment of shaft by taking readings on all couplings and also record the level of all journals.
- Refit top half cylinders and before bolting up take a further set of top blade and gland clearances to confirm the concentricity of the rotor within the cylinder.
- Remark the horizontal casing joints and refit all heavy parts. After this, take the readings for final coupling alignment and adjust it if necessary.
- After refitting the coupling bolts, refit the thrust bearings and all other bearing covers.
- Inspect turbine governor gear with stop, throttle and intercept valves.
- Dismantle other accessories and mountings if necessary and inspect service and reinstall these.
- Clean or replace the oil filters and other items of lubricating systems. Replace the lubricating oil if necessary.
- Inspect all the measuring instruments installed on the turbine and replace if necessary.
Also read:
Monday, 20 August 2012 by Unknown · 0
Goto: Page 1
B. Sequence when the turbine is in motion:
- Apply the load gradually.
- Check up the oil pressure going to the bearings and control gear.
- Observe the oil bearing temperature.
- Observe the turbine for any noise, vibration by watching the vibration and other indicators.
C. Sequence when shutting the turbine down:
- Gradually reduce the load to 0.
- Start the auxiliary oil pump and make sure that oil will be supplied to bearings at proper pressure while the turbine is coming to a stop.
- Trip the emergency valve.
- Close the leak off from the H.P glands.
- Stop the supply of cooling water to the condenser.
- Shut down the condensing equipment and open drains on turbine pipings and casings.
- Continue auxiliary oil pumps in operation untill the turbine rotor has stopped.
- Operate turning gear to rotate rotor at about 3-30 rpm for some time.
During operation, it is good practice to keep a log sheet and record the hourly readings of the instruments. Some of the readings which might prove valuable are the following:
Load on the generator throttle, steam pressure and temperature, exhaust pressure, temperature of cooling water entering and leaving the cooler, bearing oil pressure and temperature, the throttle steam flow rate, speed, frequency, vibration level.
The main requirement of steam turbine while in operation are the proper application of oil to the bearings and a continuous flow of cooling water.
Goto: Page 1
Also read:
Construction of Steam Turbines
Maintenance of Steam Turbines
Goto: Page 1
Also read:
Construction of Steam Turbines
Maintenance of Steam Turbines
by Unknown · 0
The following are the sequences of turbine operation:
A. Starting Sequence:
- Application of controlled power illuminates all of the malfunction lights. This provides a check of the malfunction lights before starting the turbines.
- Reset malfunction circuit by operating a reset switch. Malfunction lights go off and all control devices assume the condition for starting.
- Inspect the governor mechanism, till all grease cups and oil where necessary.
- Open the boiler stop valve to permit heating of the line and avoid condensation in the line.
- Open header, separator, throttle and turbine casing drills.
- Start auxiliary oil pump. This has to be stopped when the main oil pump starts delivering oil at normal pressure.
- Adjust middle valve to secure required oil pressure for the bearing.
- Start the circulating water pumps and dry vacuum pumps of the condenser. Operate the condensate extraction pumps as found necessary to remove water during the warming up period.
- Turn on the turbine steam or water seal.
- Turn on the water to the generator oil cooler and other water requiring parts.
- Keep open all the drains ahead of the throttle valve untill all water of condensation has been removed.
- Open the throttle or governor valve quickly to set the rotor in motion.
- In order to check up whether the tripping mechanism operates properly or not and to prevent the turbine from accelerating too rapidly, operate the overspeeed trip valve by using the hand lever as soon as turbine starts rolling.
- Reset the emergency overspeed valve and before the turbine comes to rest, adjust the throttle so that the turbine wheel operates between 200 and 300 rpm.
- While the rotor is in slow motion, observe any rubbing or mechanical difficulty by using a metal rod or listening device.
- As soon as the temperature of the oil leaving the bearing reaches about 40-48 C, start the circulating water through the oil coolers to maintain bearing oil temperature.
- Increase the speed gradually following the manufacturer's instructions.
- Adjust the water seal on the turbine and the atmospheric relief valve.
- Once the machine comes under the control of governor, test the emergency governor by opening the valve in the oil line to it. See that all valves controlled by this tripping mechanism close promptly. Reset open throttle valve and restore speed to normal.
- Close all drains.
- Open leak off from H.P. side gland in order to flow any excess steam to the filled water heater or to one of the lower stage of the turbine.
- Synchronize the generator and tie it in the line.
- The speed is now under the control of governor. The turbine is now ready for load and is regulated from the turbine control panel.
by Unknown · 0
From the theoretical point of view, a turbine rotor is a balanced body but in actual practice, errors of balance are introduced by various causes such as:
- Lack of homogeneity of material
- Slight error in machining.
- Difference in pitch of blades and also in individual masses
Therefore, it is essential to test balance of a complete turbine rotor and make any adjustments necessary to ensure that the balance is as good as possible. The purpose of balancing of rotors is to reduce the amplitude of vibration on a tolerable level which can be taken to be about 0.0254mm at the bearing pedestrals of a 300 rpm machine. There are two types of balancing- Static and dynamic.
1. Static Balance:
It means that the weight of the rotor is evenly disposed around the axis of the shaft. It is checked by rolling the rotor on horizontal knife edge supports.
2. Dynamic Balance:
It means that the moments of the out-of-balance weights along the axis about either bearing add upto 0. It is checked by spinning the rotor on resilient bearings detecting the vibration and adding or subtracting weights untill the vibration is negligible.
Normally, rotors are balanced at 400 rpm. The adjustment in weight is made in two planes, one at each end of the rotor by varying screwed plugs in tapped holes, or by removing metal from portion of a rim added for this purpose, or by fixing weights in a groove by means of screws. Preference is given to subtraction of weights instead of addition, since there is a chance of coming the loose weights drift.
by Unknown · 0
Types of Rotors:
There are 5 types of steam turbine rotors:
- The built-up rotor
- The integral rotor
- The hollow drum rotor
- The solid drum rotor
- The welded disc rotor
1. The Built-up Rotor:
It consists of forged steel shaft on which separate forged steel discs are shrunk and keyed. It is cheaper since the disc and shaft are relatively easy to forge and inspect for flaws and machining of these components can be carried out concurrently. Its shaft is machined with a series of stepped diameters ending with central collar. Each disc is heated and assembled on the shaft in turn, each being held in position by a form of circlip. Relative rotation is prevented either by keys, or by hub dowels known as buttons, which locate the hubs one to another to the central collar. The number of discs depend upon the number of stages which in turn depends upon the turbine output.
2. The Integral Rotor:
The shaft and wheels of this type of rotors are formed from one solid forging. Integral rotors are expensive and difficult to forge, and there is a high incidence of rejects. Over and above, a large amount of machining time and waste material are involved.
Nevertheless, the advantages are such that the are invariably used for the H.P. (high pressure) rotors on modern re-heat turbines, and sometimes for the I.P. and L.P. rotors as well. Following are the advantages of integral rotors:
- There is no chance of disc to become loose, particularly at high temperature end where at times the wheels may be hot and the shaft pull as found in the built-up rotor.
- This rotor is also free from the effect of creep which may cause the shrink fit of built-up rotor to disappear after a large number of running hours.
- The hoop stress is of lower magnitude as it contains a small hole meant for inspecting the forging.
- There is saving in axial length and reduction in spindle diameter over the built-up type.
3. Hollow Drum Rotor:
This type of rotor promotes even temperature distribution because it is designed with the same thickness of material as the casing.
4. Solid Drum Rotor:
This type of rotors are suitable for cylinders where there are lower temperatures but large diameters, as in I.P. cylinders without re-heat.
5. Welded Disc Rotor:
The last stage disc is the most heavily stressed part of the turbine and this is one of the main problem of L.P. rotor. The centrifugal load of the large rotating blades set up a tensile stress in the rim of disc, and this stress increases with decreasing radius, its maximum value being at the bore of the hub. If the bore is exceedingly small, the hoop stress becomes very less but of there is no hole, the hoop stresses throughout the disc are theoretically halved. Since there is no central hole in welded disc rotor, it suitable for L.P. rotors. It has two main advantages: It is less stressed and no need for large shaft forgings which are expensive and difficult to manufacture. The welding process and subsequent heat treatment should be performed with great attention.
by Unknown · 0
Sunday, 19 August 2012
The attachment of the turbine blades to the rotor is the most critical aspect of steam turbine design. All the forces are transmitted through the attachment to the rotor. Specially, at the low pressure end of turbines of large output, the attachment has to bear a relatively large forces due to high speed, the centrifugal force on the blade is many times its mass. Therefore it becomes necessary to estimate the stresses in the attachment but sometimes it is difficult to get the exact value. There is always the possibility of stress concentration at the sharp corners. Therefore, selection of material is very important which can safeguard from this stress concentration and that is why the calculated stress is kept reasonably low. A careful study of the forms of attachment is also necessary because occasionally it influences the shape of the wheel, rim and stresses in the disc. The form of the attachment should be such that the centrifugal force on the blade is transmitted to the disc in the simplest and most direct manner and it should give the security of attachment.
The various forms are:
The various forms are:
- De-Laval Blade root attachment
- Inverted-T attachment
- Serrated blade root arrangement (Annular fir-tree)
- Attachment for high pressure Crutis wheel
- Straddle attachment
- Modified straddle attachment
- Side entry blades attachment
- Shrouding strip attachment
- Parson's end tightened blading
- Parson's integral blades
Most of the above attachments are also used in gas turbine blading however annular fir-tree or its modified versous are most common.
Sunday, 19 August 2012 by Unknown · 0
Subscribe to:
Posts (Atom)




